Roof Replacement Timeline

Day-by-Day Project Schedule

A typical asphalt shingle re-roof takes 1-3 days for an average home once the crew is on site, but the full project — from first contractor call to final inspection — usually runs 4-8 weeks. This article walks through every stage: estimate phase (1-2 weeks), permit and material order (1-2 weeks), tear-off day (Day 1), deck inspection and underlayment (Day 1-2), shingle install (Day 2-3), cleanup and final walkthrough (Day 3), and inspector sign-off (Week 4+).